SOP- Fumigation
Objective : To lay down a procedure for fumigation using
fogger.
Scope : This procedure is applicable to the production &
QC.
Responsibility :
1.
Operator, Production is responsible to follow this SOP.
2. Production Chemist/Officer / Head of the Department
shall be responsible for the implementation of this SOP.
Procedure :
Part A : Preparation of 20% v/v Virosil Solution.
1.
Take 2 litres of cooled and filtered WFI in SS vessel.
2.
Add 0.6 Litre of concentrated solution of Virosil in
it.
3.
Make up the volume upto 3 litres with cooled &
filtered WFI.
4.
Fill the prepared 20% v/v solution of Virosil in the
tank of fogger.
Part B : Operation of Fogger
- Fumigation using fogger shall be done one day before weekly off and holiday after completion of day’s production.
- Switch off the AHU before starting the fumigation of the particular area.
- Keep the fogger filled with disinfectant on SS stool or trolley in the room.
- Switch on the main electric supply.
- Adjust the position of fogger.
- Keep the spraying level at “Average” position. The fogger will start and solution will be sprayed in the area.
Annexure – 1 Fumigation Record
Distribution : QC/ QA/Production